At a glance
  • Value £4 million
  • Client Ladhar Group Ltd
  • Sector Health Care
  • Duration 81 weeks
  • Contract JCT 2011 Intermediate Contract

Case Studies

Royal Hampton Care Home

At a glance
  • Value £4 million
  • Client Ladhar Group Ltd
  • Sector Health Care
  • Duration 81 weeks
  • Contract JCT 2011 Intermediate Contract

This care home project in Ponteland was split into two phases: the first was a traditional build whereas the second was a steel structure. Both consisted of a brick and ashlar stone outer façade to levels 1 & 2 with a render finish, and decorative clad panels to upper level 3.

The assisted living units are a timber frame system designed to reflect the main characteristics of the care home. They include disabled access platform lifts.

The roof void of the main building contains access to level 4 which includes a hair salon, nail bar, cinema, activity area and laundry room as well as the main plant room.

Key Features

  • 65 en-suite bedrooms with shower facilities
  • 4 larger suites with shower, living room and kitchen
  • Assisted living units consisting of 4 town houses and 2 bungalows
  • 2 passenger lifts
  • Dining rooms and café bar
  • Spacious landscaped gardens
  • Stone feature entrance with glass canopy and external balustrade balconies
  • Wi-Fi access
  • Selection of rooms with private patios
  • TV lounge and quiet lounge
  • Full laundry provision